I really need help understanding how to formulate into a LP. here is one of the problems i'm struggling with:


A company makes three different products: product A; product B; product C. Each product requires a piece of metal of the size:

∙ 90cm×3m for product A;
∙ 70cm×3m for product B; and
∙ 50cm×3m for product C.

The company receives metal sheets with size 2m×3m, which needs to be cut into smaller
pieces above. A large order has come in and the company needs to make at least
∙ 300 pieces of product A;
∙ 400 pieces of product B; and
∙ 1000 pieces of product C.

The company wants to find out how to cut up the metal sheets so as to minimize waste.

(a) There are 6 ways to cut a 2m×3m metal sheet into pieces of sizes 90cm×3m, 70cm×3m and 50cm×3m with a waste having the shorter side smaller than 50cm (so that no other pieces can cut out of the waste). What are they and how much metal does each one waste (list them in the order of most waste to least)?
(b) Each of the ways of cutting a metal sheet wastes a certain amount of metal. Obviously
we would like to minimize this waste while still producing enough products
A, B and C.
The cutting machine requires that there is some waste left after the
cutting. This leaves only five cutting options. Write this as a linear programming problem.

Hint. Use variables x1, . . . , x5, where xi denotes the number metal sheets cut using option i. Your goal is to satisfy the production requirements while minimizing the waste.


I'd appreciate any help regarding this problem.
Reply With Quote
Advertisement
 
  #2  
Old July 21st, 2009, 11:39 PM
CaptainBlack's Avatar
Grand Panjandrum
 
Join Date: Nov 2005
Location: South of England
Posts: 12,285
Country:
Thanks: 779
Thanked 4,005 Times in 3,230 Posts
CaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond repute
Default

Quote:
Originally Posted by ThineBlood View Post
Hi everyone,
I really need help understanding how to formulate into a LP. here is one of the problems i'm struggling with:


A company makes three different products: product A; product B; product C. Each product requires a piece of metal of the size:

∙ 90cm×3m for product A;
∙ 70cm×3m for product B; and
∙ 50cm×3m for product C.

The company receives metal sheets with size 2m×3m, which needs to be cut into smaller
pieces above. A large order has come in and the company needs to make at least
∙ 300 pieces of product A;
∙ 400 pieces of product B; and
∙ 1000 pieces of product C.

The company wants to find out how to cut up the metal sheets so as to minimize waste.

(a) There are 6 ways to cut a 2m×3m metal sheet into pieces of sizes 90cm×3m, 70cm×3m and 50cm×3m with a waste having the shorter side smaller than 50cm (so that no other pieces can cut out of the waste). What are they and how much metal does each one waste (list them in the order of most waste to least)?
(b) Each of the ways of cutting a metal sheet wastes a certain amount of metal. Obviously
we would like to minimize this waste while still producing enough products
A, B and C.
The cutting machine requires that there is some waste left after the
cutting. This leaves only five cutting options. Write this as a linear programming problem.

Hint. Use variables x1, . . . , x5, where xi denotes the number metal sheets cut using option i. Your goal is to satisfy the production requirements while minimizing the waste.


I'd appreciate any help regarding this problem.
Before formulating this as a LP you need to do part (a). Have you done it, and what are the ways?

CB
__________________
Truth does not change because it is, or is not, believed by a majority of the people.

Giordano Bruno
Reply With Quote
  #3  
Old July 22nd, 2009, 07:02 PM
Newbie
 
Join Date: Jul 2009
Posts: 7
Thanks: 0
Thanked 1 Time in 1 Post
ThineBlood is on a distinguished road
Default

Quote:
Originally Posted by CaptainBlack View Post
Before formulating this as a LP you need to do part (a). Have you done it, and what are the ways?

CB

I'm not sure if this is what i was supposed to do but i've got.

2 (90cmx3m) + 20 cmx3m (waste)
4 (50cmx3m) + 0 (waste)
1 (90cmx3m) + 2 (50cmx3m) + 10 cmx3m (waste)
2 (70cmx3m) + 1 (50cmx3m) + 10 cmx3m (waste)
1 (90cmx3m) + 1 (70cmx3m) + 40 cmx3m (waste)
1 (70cmx3m) + 2 (50cmx3m) + 30 cmx3m (waste)


Thanks for your help CaptainBlack, I really appreciate it.
Reply With Quote
  #4  
Old July 22nd, 2009, 08:38 PM
CaptainBlack's Avatar
Grand Panjandrum
 
Join Date: Nov 2005
Location: South of England
Posts: 12,285
Country:
Thanks: 779
Thanked 4,005 Times in 3,230 Posts
CaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond repute
Default

Quote:
Originally Posted by ThineBlood View Post
I'm not sure if this is what i was supposed to do but i've got.

2 (90cmx3m) + 20 cmx3m (waste)
4 (50cmx3m) + 0 (waste)
1 (90cmx3m) + 2 (50cmx3m) + 10 cmx3m (waste)
2 (70cmx3m) + 1 (50cmx3m) + 10 cmx3m (waste)
1 (90cmx3m) + 1 (70cmx3m) + 40 cmx3m (waste)
1 (70cmx3m) + 2 (50cmx3m) + 30 cmx3m (waste)


Thanks for your help CaptainBlack, I really appreciate it.
OK that is what we needed (other than the question requests them ordered form least to most waste.

Also for the nest stage as the machine requires some waste you need a new list with the zero waste cutting method dropped.

You are told (it is the hint) to use variables x_1,\ ...\ x_5 for the number of pieces cut using each of the cutting methods.

Then we have to express each of the production rquirements as an inequality of the variables x_1,\ ...\ x_5, these are the constraints (together with the non-negativity constraints on the variables), and the objective to minimise the total waste.

CB
__________________
Truth does not change because it is, or is not, believed by a majority of the people.

Giordano Bruno
Reply With Quote
  #5  
Old July 23rd, 2009, 10:10 PM
Newbie
 
Join Date: Jul 2009
Posts: 7
Thanks: 0
Thanked 1 Time in 1 Post
ThineBlood is on a distinguished road
Default

Quote:
Originally Posted by CaptainBlack View Post
OK that is what we needed (other than the question requests them ordered form least to most waste.

Also for the nest stage as the machine requires some waste you need a new list with the zero waste cutting method dropped.

You are told (it is the hint) to use variables x_1,\ ...\ x_5 for the number of pieces cut using each of the cutting methods.

Then we have to express each of the production rquirements as an inequality of the variables x_1,\ ...\ x_5, these are the constraints (together with the non-negativity constraints on the variables), and the objective to minimise the total waste.

CB
so this is the part i don't entirely understand. what are x_1,\ ...\ x_5 represent. I don't understand what the number of sheets cut using option i mean. does it mean that if I cut a 2mx3m sheet once then i use the variable x_1?
Reply With Quote
  #6  
Old July 23rd, 2009, 11:54 PM
CaptainBlack's Avatar
Grand Panjandrum
 
Join Date: Nov 2005
Location: South of England
Posts: 12,285
Country:
Thanks: 779
Thanked 4,005 Times in 3,230 Posts
CaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond repute
Default

Quote:
Originally Posted by ThineBlood View Post
so this is the part i don't entirely understand. what are x_1,\ ...\ x_5 represent. I don't understand what the number of sheets cut using option i mean. does it mean that if I cut a 2mx3m sheet once then i use the variable x_1?
Order the cutting methods in increasing order of waste (like you have been asked to do in part (a)) and drop the one with zero waste.

Lable these cut1 .. cut5. Now x_i represents the number of sheets of steel you will cut using cuti.

CB
__________________
Truth does not change because it is, or is not, believed by a majority of the people.

Giordano Bruno
Reply With Quote
  #7  
Old July 24th, 2009, 04:27 AM
Newbie
 
Join Date: Jul 2009
Posts: 7
Thanks: 0
Thanked 1 Time in 1 Post
ThineBlood is on a distinguished road
Default

Quote:
Originally Posted by CaptainBlack View Post
Order the cutting methods in increasing order of waste (like you have been asked to do in part (a)) and drop the one with zero waste.

Lable these cut1 .. cut5. Now x_i represents the number of sheets of steel you will cut using cuti.

CB
so would these be my constraints?

x_1 + 2x_3 + x_5 >= 300,
2x_2 + x_4 + x_5 >= 400,
2x_1 + x_2 + x_4 >=1000,

and objective function:

Minimize 10x_1 + 10x_2 + 20x_3 + 30x_4 + 40x_5

x_1,...x_5 >= 0
Reply With Quote
  #8  
Old July 24th, 2009, 06:43 AM
CaptainBlack's Avatar
Grand Panjandrum
 
Join Date: Nov 2005
Location: South of England
Posts: 12,285
Country:
Thanks: 779
Thanked 4,005 Times in 3,230 Posts
CaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond repute
Default

Quote:
Originally Posted by ThineBlood View Post
so would these be my constraints?

x_1 + 2x_3 + x_5 >= 300,
2x_2 + x_4 + x_5 >= 400,
2x_1 + x_2 + x_4 >=1000,

and objective function:

Minimize 10x_1 + 10x_2 + 20x_3 + 30x_4 + 40x_5

x_1,...x_5 >= 0
That looks OK-ish, its a bit difficult to check with the cuts unordered and in a different post.

CB
__________________
Truth does not change because it is, or is not, believed by a majority of the people.

Giordano Bruno
Reply With Quote
  #9  
Old July 24th, 2009, 07:48 AM
Newbie
 
Join Date: Jul 2009
Posts: 7
Thanks: 0
Thanked 1 Time in 1 Post
ThineBlood is on a distinguished road
Default

Quote:
Originally Posted by CaptainBlack View Post
That looks OK-ish, its a bit difficult to check with the cuts unordered and in a different post.

CB
1 (90cmx3m) + 2 (50cmx3m) + 10 cmx3m (waste)
2 (70cmx3m) + 1 (50cmx3m) + 10 cmx3m (waste)
2 (90cmx3m) + 20 cmx3m (waste)
1 (70cmx3m) + 2 (50cmx3m) + 30 cmx3m (waste)
1 (90cmx3m) + 1 (70cmx3m) + 40 cmx3m (waste)

x_1 + 2x_3 + x_5 >= 300,
2x_2 + x_4 + x_5 >= 400,
2x_1 + x_2 + x_4 >=1000,


Thank you so much for all ur help, CaptainBlack. I really appreciate it.
Reply With Quote
  #10  
Old July 24th, 2009, 07:59 AM
CaptainBlack's Avatar
Grand Panjandrum
 
Join Date: Nov 2005
Location: South of England
Posts: 12,285
Country:
Thanks: 779
Thanked 4,005 Times in 3,230 Posts
CaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond reputeCaptainBlack has a reputation beyond repute
Default

Quote:
Originally Posted by ThineBlood View Post
1 (90cmx3m) + 2 (50cmx3m) + 10 cmx3m (waste)
2 (70cmx3m) + 1 (50cmx3m) + 10 cmx3m (waste)
2 (90cmx3m) + 20 cmx3m (waste)
1 (70cmx3m) + 2 (50cmx3m) + 30 cmx3m (waste)
1 (90cmx3m) + 1 (70cmx3m) + 40 cmx3m (waste)

x_1 + 2x_3 + x_5 >= 300,
2x_2 + x_4 + x_5 >= 400,
2x_1 + x_2 + x_4 >=1000,


Thank you so much for all ur help, CaptainBlack. I really appreciate it.
∙ 90cm×3m for product A;
∙ 70cm×3m for product B; and
∙ 50cm×3m for product C.

The company receives metal sheets with size 2m×3m, which needs to be cut into smaller
pieces above. A large order has come in and the company needs to make at least
∙ 300 pieces of product A;
∙ 400 pieces of product B; and
∙ 1000 pieces of product C.

I make it:

x_1 + 2x_3 + x_5 >= 300,
2x_2 + x_4 + x_5 >= 400,
2x_1 + x_2 + 2x_4 >=1000,

CB
__________________
Truth does not change because it is, or is not, believed by a majority of the people.

Giordano Bruno
Reply With Quote
The following users thank CaptainBlack for this useful post:
Donate to MHF
  #11  
Old July 24th, 2009, 10:23 PM
Newbie
 
Join Date: Jul 2009
Posts: 7
Thanks: 0
Thanked 1 Time in 1 Post
ThineBlood is on a distinguished road
Default

Quote:
Originally Posted by CaptainBlack View Post
∙ 90cm×3m for product A;
∙ 70cm×3m for product B; and
∙ 50cm×3m for product C.

The company receives metal sheets with size 2m×3m, which needs to be cut into smaller
pieces above. A large order has come in and the company needs to make at least
∙ 300 pieces of product A;
∙ 400 pieces of product B; and
∙ 1000 pieces of product C.

I make it:

x_1 + 2x_3 + x_5 >= 300,
2x_2 + x_4 + x_5 >= 400,
2x_1 + x_2 + 2x_4 >=1000,

CB

oh yes, i wrote the same thing in my notes.

Thanks for all ur help.
Reply With Quote
The following users thank ThineBlood for this useful post:
Donate to MHF
  #12  
Old July 31st, 2009, 04:08 AM
Junior Member
 
Join Date: Jul 2009
Posts: 32
Thanks: 27
Thanked 3 Times in 2 Posts
MAX09 is on a distinguished road
Thumbs up @Thine Blood and Captain Black

Thanks for sharing the procedure of the LPP's formulation;
It really helped:

MAX
__________________
~I have to find the truly original idea - that's the only way I will ever distinguish myself - it's the only way I'll ever...matter.~
Reply With Quote
Reply

Tags
formulate into lp, linear programming

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off
Forum Jump


All times are GMT -7. The time now is 10:01 PM.


Powered by vBulletin® Version 3.7.3
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.
SEO by vBSEO 3.2.0 ©2008, Crawlability, Inc.
©2005 - 2009 Math Help Forum


Math Help Forum is a community of maths forums with an emphasis on maths help in all levels of mathematics.
Register to post your math questions or just hang out and try some of our math games or visit the arcade.